Updating task status updates resource status
| Registry value | auto track resources |
| Group Policy | Updating task status updates resource status |
| German version | Aktualisierung des Vorgangsstatus aktualisiert den Ressourcenstatus |
| Intune settings catalog | Updating task status updates resource status (User) |
| Scope | User · HKCU |
| ADMX | proj16.admx · L_PjUpdatingTask |
Group Policy path
Registry
| Value | Data |
|---|---|
HKCU\Software\policies\microsoft\office\16.0\ms project\options\calculation | |
| auto track resources | Enabled = 1 · Disabled = 0 |
Not configured = the value does not exist – the application default applies and users may change the setting.
PowerShell
Check the current value (read-only)
# --- Settings ---
$root = 'HKCU:' # other signed-in user (elevated): 'Registry::HKEY_USERS\<SID>'
$key = "$root\Software\policies\microsoft\office\16.0\ms project\options\calculation"
foreach ($name in @('auto track resources')) {
try { '{0} = {1}' -f $name, (Get-ItemPropertyValue -Path $key -Name $name -ErrorAction Stop) }
catch { '{0}: not configured' -f $name }
}Admin rights needed: HKCU\Software\Policies is read-only for standard users. An elevated session writes to the admin's own HKCU – to set it for another signed-in user, change $root to Registry::HKEY_USERS\<SID>.
Enable
# --- Settings ---
$root = 'HKCU:' # other signed-in user (elevated): 'Registry::HKEY_USERS\<SID>'
try {
$key = "$root\Software\policies\microsoft\office\16.0\ms project\options\calculation"
if (-not (Test-Path $key)) { New-Item -Path $key -Force -ErrorAction Stop | Out-Null }
New-ItemProperty -Path $key -Name 'auto track resources' -PropertyType DWord -Value 1 -Force -ErrorAction Stop | Out-Null # Enabled
'Done.'
}
catch { Write-Error "Failed: $($_.Exception.Message)" }Disable
# --- Settings ---
$root = 'HKCU:' # other signed-in user (elevated): 'Registry::HKEY_USERS\<SID>'
try {
$key = "$root\Software\policies\microsoft\office\16.0\ms project\options\calculation"
if (-not (Test-Path $key)) { New-Item -Path $key -Force -ErrorAction Stop | Out-Null }
New-ItemProperty -Path $key -Name 'auto track resources' -PropertyType DWord -Value 0 -Force -ErrorAction Stop | Out-Null # Disabled
'Done.'
}
catch { Write-Error "Failed: $($_.Exception.Message)" }Reset to Not configured
# --- Settings --- $root = 'HKCU:' # other signed-in user (elevated): 'Registry::HKEY_USERS\<SID>' $key = "$root\Software\policies\microsoft\office\16.0\ms project\options\calculation" Remove-ItemProperty -Path $key -Name 'auto track resources' -ErrorAction SilentlyContinue 'Policy values removed (Not configured).'
Intune (settings catalog)
Updating task status updates resource status (User)
Settings catalog → Add settings → search for the name above.
Intune Settings Catalog Viewer ↗
Alternative: custom profile (OMA-URI)
| OMA-URI | ./User/Vendor/MSFT/Policy/Config/proj16v2~Policy~L_Proj~L_ProjectOptions~L_PjCalculation~L_PjCalcProjectFile/L_PjUpdatingTask |
| Data type | String |
| Value | <enabled/> · <disabled/> |
Cloud Policy
Cloud Policy (config.office.com → Customization → Policy Management) offers many user policies of the Microsoft 365 Apps – search for Updating task status updates resource status. It also applies to unmanaged devices and wins over GPO and Intune for the same setting.
Microsoft explanation
Automatically updates resource status, such as actual and remaining work and cost, whenever you update task status, such as percent complete, actual duration, or remaining duration.
If you enable this setting, task status updates are automatically applied to resources.
If you disable or do not configure this setting, the user's default setting is used.
Same category: Microsoft Project 2016 › Project Options › Calculation › Calculation options for 'Project1'
- Move start of remaining parts before status date forward to status datemoveremaining
- And move end of completed parts forward to status dateandmovecompleted
- Move end of completed parts after status date back to status datemovecompleted
- And move start of remaining parts back to status dateandmoveremaining
- Edits to total task % complete will be spread to the status dateedits to total task %complete will be spread to the status date
- Inserted projects are calculated like summary tasksinserted projects are calculated like summary tasks
- Actual costs are always calculated by Microsoft Projectactual costs are always calculated by microsoft office project
- Edits to total actual cost will be spread to the status dateedits to total actual cost will be spread to the status date
- Default fixed costs accrualdefault fixed costs accrual
- Calculate multiple critical pathscalculate multiple critical paths
- Tasks are critical if slack is less than or equal toshow as critical if slack
All policies in this category · All 140 policies of proj16.admx