Inserted projects are calculated like summary tasks
| Registry value | inserted projects are calculated like summary tasks |
| Group Policy | Inserted projects are calculated like summary tasks |
| German version | Eingefügte Projekte werden wie Sammelvorgänge berechnet |
| Intune settings catalog | Inserted projects are calculated like summary tasks (User) |
| Scope | User · HKCU |
| ADMX | proj16.admx · L_PjInsertedProjects |
Group Policy path
Registry
| Value | Data |
|---|---|
HKCU\Software\policies\microsoft\office\16.0\ms project\options\calculation | |
| inserted projects are calculated like summary tasks | Enabled = 1 · Disabled = 0 |
Not configured = the value does not exist – the application default applies and users may change the setting.
PowerShell
Check the current value (read-only)
# --- Settings ---
$root = 'HKCU:' # other signed-in user (elevated): 'Registry::HKEY_USERS\<SID>'
$key = "$root\Software\policies\microsoft\office\16.0\ms project\options\calculation"
foreach ($name in @('inserted projects are calculated like summary tasks')) {
try { '{0} = {1}' -f $name, (Get-ItemPropertyValue -Path $key -Name $name -ErrorAction Stop) }
catch { '{0}: not configured' -f $name }
}Admin rights needed: HKCU\Software\Policies is read-only for standard users. An elevated session writes to the admin's own HKCU – to set it for another signed-in user, change $root to Registry::HKEY_USERS\<SID>.
Enable
# --- Settings ---
$root = 'HKCU:' # other signed-in user (elevated): 'Registry::HKEY_USERS\<SID>'
try {
$key = "$root\Software\policies\microsoft\office\16.0\ms project\options\calculation"
if (-not (Test-Path $key)) { New-Item -Path $key -Force -ErrorAction Stop | Out-Null }
New-ItemProperty -Path $key -Name 'inserted projects are calculated like summary tasks' -PropertyType DWord -Value 1 -Force -ErrorAction Stop | Out-Null # Enabled
'Done.'
}
catch { Write-Error "Failed: $($_.Exception.Message)" }Disable
# --- Settings ---
$root = 'HKCU:' # other signed-in user (elevated): 'Registry::HKEY_USERS\<SID>'
try {
$key = "$root\Software\policies\microsoft\office\16.0\ms project\options\calculation"
if (-not (Test-Path $key)) { New-Item -Path $key -Force -ErrorAction Stop | Out-Null }
New-ItemProperty -Path $key -Name 'inserted projects are calculated like summary tasks' -PropertyType DWord -Value 0 -Force -ErrorAction Stop | Out-Null # Disabled
'Done.'
}
catch { Write-Error "Failed: $($_.Exception.Message)" }Reset to Not configured
# --- Settings --- $root = 'HKCU:' # other signed-in user (elevated): 'Registry::HKEY_USERS\<SID>' $key = "$root\Software\policies\microsoft\office\16.0\ms project\options\calculation" Remove-ItemProperty -Path $key -Name 'inserted projects are calculated like summary tasks' -ErrorAction SilentlyContinue 'Policy values removed (Not configured).'
Intune (settings catalog)
Inserted projects are calculated like summary tasks (User)
Settings catalog → Add settings → search for the name above.
Intune Settings Catalog Viewer ↗
Alternative: custom profile (OMA-URI)
| OMA-URI | ./User/Vendor/MSFT/Policy/Config/proj16v2~Policy~L_Proj~L_ProjectOptions~L_PjCalculation~L_PjCalcProjectFile/L_PjInsertedProjects |
| Data type | String |
| Value | <enabled/> · <disabled/> |
Cloud Policy
Cloud Policy (config.office.com → Customization → Policy Management) offers many user policies of the Microsoft 365 Apps – search for Inserted projects are calculated like summary tasks. It also applies to unmanaged devices and wins over GPO and Intune for the same setting.
Microsoft explanation
Specifies that a single critical path is calculated throughout the master project, by treating inserted projects as summary tasks in the master project.
If you enable this setting, the critical path is calculated by treating inserted projects as summary tasks.
If you disable or do not configure this setting, the user's default setting is used.
Same category: Microsoft Project 2016 › Project Options › Calculation › Calculation options for 'Project1'
- Updating task status updates resource statusauto track resources
- Move start of remaining parts before status date forward to status datemoveremaining
- And move end of completed parts forward to status dateandmovecompleted
- Move end of completed parts after status date back to status datemovecompleted
- And move start of remaining parts back to status dateandmoveremaining
- Edits to total task % complete will be spread to the status dateedits to total task %complete will be spread to the status date
- Actual costs are always calculated by Microsoft Projectactual costs are always calculated by microsoft office project
- Edits to total actual cost will be spread to the status dateedits to total actual cost will be spread to the status date
- Default fixed costs accrualdefault fixed costs accrual
- Calculate multiple critical pathscalculate multiple critical paths
- Tasks are critical if slack is less than or equal toshow as critical if slack
All policies in this category · All 140 policies of proj16.admx